New Transportation and Maintenance Facility is Complete


The transportation project was nearly nine years in the making. The previous facility, a former elementary school built in 1936, lacked the space for secure and safe bus storage, maintenance and employee parking. The sale of that property and 70% reimbursement for transportation improvements from the State of Oregon made this development possible without the use of general fund dollars for 5-7 years. This facility has significantly improved operational efficiencies for both transportation and facility services. 

Project Timeline 

  • August 3, 2015 - Groundbreaking Ceremony
  • Early Permit Start 10-12-15
  • Footings 10-23-15
  • Slab on Grade Pour 11-23-15
  • Erect Tilt Panels 12-22-15 (pending holidays)
  • Building Dry-in 2/5/16
  • Windows complete 3/7/16
  • Overhead MEP Rough In complete 2-18-16
  • Wall Framing complete 2-25-16
  • Drywall Complete 3-8-16
  • Doors and hardware 4-5-16
  • Landscaping Complete 5-15-16
  • Finishes Complete  5-31-16
  • Temporary Occupancy 6-16-16
  • Commissioning Complete 7-15-16